
On the original Tangguh LNG project (trains 1 & 2), BP depended on EPC contractors’ systems. This resulted in challenges with:
From this experience, BP identified a key element for successfully delivering the Tangguh Expansion Project:
The system must be both document-centric and data-centric — capable of handling, collecting and validating documents and data automatically, while enabling collaborative working across BP, EPC contractors and suppliers.
The Tangguh Expansion Project in Indonesia included:
The project had a CAPEX of approximately $8 billion USD and delivered its first LNG cargo in October 2023.
From FEED in 2014 through start-up in 2023, the project generated:
Managing this volume of information across seven EPC contractors required more than traditional document control.
BP defined that the required system must:
Following successful use on the BP Quad 204 project, the Sharecat platform met all defined requirements and was selected and implemented.
The Sharecat platform was used from early phase design (FEED), through detail design and execution, construction and commissioning, and into start-up and early operations.
The platform functionality included:
A single workspace supported the entire project from 2014 to 2023, including running a competitive FEED with two EPC consortia in full segregation.
BP summarised their experience as follows:
“In my experience most solutions normally struggle to meet expectations and demands of users, but from the moment I first came across Sharecat it frankly blew my mind. When comparing the value provided to the cost spent, the Sharecat platform definitely has been a very good investment for us.”
— Dodi Jatikusuma, Project Information Management Manager – BP Tangguh LNG
Key benefits identified included:
Because asset data was structured and validated during project execution:
This enabled seamless interaction between project and operations teams and supported staged start-ups alongside the live trains 1 & 2 facility.
During execution, the COVID-19 pandemic required the construction team at site to reduce from approximately 10,000 to fewer than 2,000 personnel.
As a cloud-based SaaS solution, the Sharecat platform enabled the project to transition to remote working without suspension of detail engineering design, commissioning or construction activities.
“Without Sharecat being a cloud-based system we would have been unlikely to be able to continue with detail engineering design, commissioning and construction activities during the COVID restrictions.”
— Dodi Jatikusuma, BP
The success of the Tangguh Expansion Project has resulted in BP continuing to use Sharecat for the new UCC project at Tangguh, aimed at reducing carbon emissions through offshore CO₂ injection while enhancing gas recovery.
The Tangguh LNG Expansion Project demonstrates that managing capital projects at scale requires more than document control.
It requires:
By combining document management and data management within a single scalable platform, Sharecat enabled BP to deliver an $8 billion LNG expansion with controlled information, measurable cost savings, and seamless transition into operations.